Expect a design phase before construction. For a job that changes walls or adds space, the remodeler or a designer draws plans, and the building permit package goes to Building, Inspections & Zoning on paper. The plumber and electrician file their own permits, usually through SmartGov.
Construction follows a predictable sequence: demolition, framing, rough plumbing and wiring, inspections, insulation, waterproofing, tile, fixtures, and glass. Under the schedule that began October 15, 2026, the building office is open Monday to Thursday, so inspection timing should be planned around that week.
A primary suite project can run several weeks or more. Ask how the crew will protect the rest of the second floor and what you'll use for a bathroom in the meantime.